Capital Projects

🚧 Mildred Phase 2

Mildred Phase 2 Sanitary Sewer Improvement Project

📋 Project Overview

Status: Construction Starting Soon

The Mildred Phase 2 Sanitary Sewer Improvement Project will extend central sewer service into the Quincy Road area in Kirbyville, an area where homes and businesses are currently served by onsite septic systems. The project will serve approximately 56 connections initially and is being constructed with funds provided by the Taney County Sewer Sales Tax.

Wastewater collected by the project will be conveyed through the District’s existing Kirbyville/Coon Creek collection system to the City of Hollister Regional Wastewater Treatment Facility for treatment. The construction contract was awarded to Excel Excavating, and construction is expected to take approximately 12 months to complete.

The District will provide a full connection and decommissioning of each septic tank at no cost to the homeowner. Properties with a habitable structure will be required to connect to the new sewer system, and the District will need a signed Sewer Connection Agreement to make the connection. If you have not signed a connection agreement, please contact TCRSD Construction Project Manager Travis Tucker at 417-827-3720 as soon as possible.

During construction, the neighborhood will be impacted by periodic road and driveway closures, yard and landscape disturbances, and elevated noise levels from equipment. The District will do its best to communicate and address problems and concerns as quickly as possible, and once construction is complete, the neighborhood and roads will be restored. Property owners who rent to others are asked to let their renters know about the construction and its potential impacts to the area.

Project Area
Quincy Road, Kirbyville
Initial Connections
Approx. 56
Contractor
Excel Excavating
Construction Time
Approx. 12 Months

🗺️ See the Project Area

View the Mildred Phase 2 project area on the TCRSD GIS Sewer Map to see how the project relates to your property. Proposed line and manhole locations are subject to change.

Open System Map →

❓ Frequently Asked Questions

Mildred Phase 2 Sewer Project Construction

General

Why do we need this sewer project? +

This sewer project is planned for an area where all homes and businesses are currently served by onsite septic systems. Onsite septic systems are prone to failure and installing central sewers will eliminate poorly treated wastewater from entering our areas lakes, streams, and drinking water supplies.

What does the Sewer District do for me? +

During construction, the Sewer District installs the wastewater collection system including the final connection to the home. We will properly close out your septic tank and move all wastewater generated to an approved treatment facility. This reduces the source of wastewater infiltration into private wells and area lakes and streams.

Who will be affected? +

This will benefit all residents in the Mildred Phase 2 area as shown on the project map. Not all properties will be impacted by the construction of the sewer mains, but all will likely be affected during the service line connection phase.

What does the project include? +

The construction of all infrastructure (main lines, manholes, and lift stations) necessary to operate the collection system. Also included are the connection of homes and businesses through the installation of service lines and grinder pumps where applicable, including the decommissioning of the existing septic tanks along with restoration of all disturbed areas.

How long does construction take? +

This project is scheduled to be completed within approximately twelve months from the start of construction.

Will road and driveway closures and detours be necessary during construction? +

Road and driveway closures will occur on a temporary basis and will move along with the construction. The contractor will communicate all temporary driveway closures ahead of time.

Will the sewer project include my property? +

All properties will be affected during the connection phase. Not all properties will be impacted by the construction of the sewer mains and lift stations. Please view the project map to see the map concerning your property or contact the District.

If I have an issue on my property during construction, who do I contact? +

If you have an issue that needs to be discussed, please contact TCRSD Construction Project Manager Travis Tucker at 417-827-3720.

Connection to Sewer

What do I have to do to get sewer service? +

If you have not signed a sewer service connection agreement, please contact Travis Tucker at 417-827-3720. At the time your home or business is connected you will also be required to complete a billing application. This can be done by calling our office at 417-544-0655 or online at tcrsd.org under the “How Do I” link then “Submit a Billing Application.”

Who can, and who must, connect to the new sewer lines? +

All structures will be required to connect. The District is completing this work; there is no cost to the property owner during the construction phase. Delayed connection by the property owner may result in the property owner being responsible for connecting their home to the sewer system and paying all associated costs to do so.

Will I be forced to remove my septic tank? +

The Missouri Department of Natural Resources and the District have regulations for the removal of inactive septic tanks and this will be facilitated during construction by the District’s contractor.

What happens to my septic tank after I get sewer service? +

During the connection phase of the project the tank will be pumped of all contents, holes broke in the bottom, and the top broken up or removed, and then the tank will be backfilled with gravel and the surrounding area restored.

What will be done and who is responsible for gray water lines? +

All sewer lines coming from a building must be connected to the sewer system, including gray water lines. Property owners should notify the District to the location of gray water lines so they may be properly connected.

Who pays for the connection? +

During construction the Sewer District will fund all expenses for connection. Delayed connection by the property owner may be at the expense of the property owner.

Billing

What are the monthly sewer rates? +

The District currently charges a flat rate of $40.00 per Residential structure per month. Commercial/Non-residential properties are based on meter readings taken from the property’s water meter and are charged $40.00 for the first 2,000 gallons per month and then $8.50 per additional 1,000 gallons per month.

What is the billing cycle? +

The billing cycle is monthly and the District bills in the arrears. Bills are generally sent out for the previous month on the 5th and are due by the 25th. We offer several ways to pay your bill including cash, check, credit card, or automatic bank draft (ACH). See our Payment Options page for details.

I have two homes on my property, what will my monthly bill be? +

Your bill would be $80 per month (2 homes times $40 each). TCRSD bills for each structure separately that is connected to the sewer system and all buildings that are habitable and have toilet facilities in them are required to be connected to the sewer system.

Will I be charged for connecting? +

Connections made during construction of the project will be at no cost to the property owner. New buildings built and connected up to one year after the construction project is complete will not be charged a connection/capacity fee but still must be permitted and inspected by the District.

If I do not use the sewer system will I still be required to pay for it? +

If a property is vacant without any habitable structures, there is no monthly charge. However, all habitable structures will be required to connect to the sewer system and will be charged monthly regardless if the building is occupied or not. The District does offer a Voluntary Shut-off Agreement whereby a property owner may reduce their monthly sewer bill in the event of long absences where no one is living on the property. Please refer to our VSO Program page for more information.

My property is a rental property, how is this handled? +

All sewer charges are the sole responsibility of the property owner. The District will accept payments from renters or tenants, but the property owner is always ultimately responsible for the sewer charges and will receive a bill for their property each month.

Will vacant lots have to pay? +

There is no charge where there is no connection. Future buildings connected on the vacant lot will incur connection/capacity fees and monthly charges.

📞 I Still Have Questions

Who to contact about the Mildred Phase 2 project

Construction Project Manager
Travis Tucker
Construction questions, connection agreements, and on-property issues
417-827-3720
TCRSD Office
Billing & General Information
Billing questions and billing applications
417-544-0655
Engineer of Record
Toth & Associates
Project design and engineering — Springfield, MO
417-888-0645